What a Big Customer's Audit Taught Us About Planning Laminated Film
In 2024, a large customer in logistics and packaging sent a team to audit us as a supplier of printed laminated film. We had prepared for questions on inks, adhesives and quality paperwork.
Those went fine.
The hard questions were about our production plan.
In plain words, the audit showed that our plan for laminated film changed too often, and that jobs entered the plan before we knew the material and cylinders were ready. We fixed it with a frozen plan window, a readiness check, hold points between stages, a daily plan review and job tracking in our ERP. This post is what we learned. If you buy pouches or laminated rolls, it will also tell you what to ask your own supplier.
Why laminated film is harder to plan than it looks
A printed laminate is not made on one machine. It moves through four stages, and each one waits for the one before it.
- Printing. The outer film (often PET or BOPP) is printed on a rotogravure machine with one cylinder per colour, so a 6-colour design needs 6 cylinders ready and proofed.
- Lamination. The printed film is bonded to a second film, sometimes a third, with adhesive.
- Curing. The laminated rolls rest until the adhesive sets fully. This takes time, and you cannot rush chemistry.
- Slitting. The cured jumbo roll is cut to the customer's width and roll length, then packed.
Curing is like setting curd at home. You can check it, worry about it and open the lid ten times, but it will set only in its own time. So a delay of a few hours at printing does not stay small.
It pushes lamination, then curing, then slitting, and the dispatch date moves.
What the audit found
The auditor asked us to show where one running job stood at that moment. We could not answer from a screen. Someone had to walk to the floor and ask.
That one question opened up the rest.
- Our plan changed many times a week. An urgent call from one customer pushed another customer's job down the list. Sales often said yes before production knew about it.
- Jobs entered the plan before material was in the store. If the film or adhesive arrived late, the printing machine waited, or we swapped jobs at the last minute.
- Cylinders were not checked at the planning stage. A new design's cylinders could still be at the engraver, or an old set could need re-chroming, and we found out only at make-ready.
- There were no clear hold points between stages. A shade or register problem from printing could be caught only at slitting, after we had already spent the second film and the adhesive on it.
- Work in progress was not visible. Rolls sat in curing and nobody outside the floor knew which job they belonged to or when they would be ready.
I will be honest about the cause. Most of this came from me.
I had built a habit of saying yes to every urgent request, and the plan paid the price for it every week.
The five changes we made
We did not buy new machines for this. We changed how a job gets into the plan and how it moves through it.
- A frozen plan window. Once a job is inside the next 48 hours, it does not move unless the plant head and I both agree. Urgent orders go into the first open slot after the window.
- A readiness check before a job enters the plan. Film in stock and tested, inks and adhesive available, cylinders received and proofed, artwork approved in writing by the customer. If one item is missing, the job waits outside the plan, not inside it.
- Hold points between stages. The first printed roll is checked against the approved shade and signed before the rest of the run. Before slitting, we record the curing time and check bond strength. Before packing, we check width, core and joints.
- A daily production meeting. Production, stores, quality and sales sit together every morning, look at the same plan and agree on the day. Problems now come up at 10 in the morning instead of at dispatch.
- Tracking in our ERP. Every job is a production order in SAP Business One, and each stage is booked as it finishes. When a customer asks where their job is, we can answer from the screen.
What changed, and what did not
The dates we give are more honest now. We have fewer last-minute swaps on the printing line, and fewer rolls rejected at slitting for problems that started at printing.
It is not perfect.
A frozen window means we sometimes tell a buyer that an urgent order cannot start this week. Some buyers do not like hearing that. I would rather say it on the first day than on the day of dispatch.
Our ISO 9001:2015 certificate (audited by Intertek) and our ZED Gold rating are on our certifications page. The standard asks for planned and controlled production. The audit showed us what that really means on a busy afternoon when three urgent calls come in together.
Questions to ask your laminate supplier
You do not need to audit a supplier to learn a lot. Ask these five questions on your next call.
- How many days ahead is your production plan frozen?
- Do you check cylinders and material before you give me a date?
- How long do you cure before slitting, and is it recorded for each job?
- Can you tell me the stage of my job today without calling the floor?
- What happens to a roll that fails at a hold point?
A supplier who answers all five clearly is one who will keep dates. A supplier who says "don't worry, sir" to all five is one to watch.
We have been making packaging in Jaipur since 1997, and today we make printed food packaging pouches and laminated film for buyers in India and 20+ countries. Food-contact packs are made only from virgin material.
I am still grateful to that audit team. They gave us a free lesson that our own reviews had missed for years.